Design Verification, Validation and Transfer Under ISO 13485: Sample Sizes, Representative Product and Production Readiness
Reviewed by Aaron Lyon, President of A.P. Lyon and former Director of Quality Assurance and International Regulatory, with more than 30 years in medical device quality. Last reviewed November 27, 2026.
The end of a design project is where the evidence is made. Verification shows the design meets its requirements. Validation shows the device meets the users' needs. Transfer shows production can make it. Each has its own requirements in ISO 13485, and each is a frequent source of audit findings when the plan, the sample size or the product used is not recorded.
This guide covers the three, in order. Each summary of a requirement is in our own words. For the start of the project, see Design Inputs and the Trace Matrix. For the whole route, see Design Controls Step by Step Under ISO 13485 and the FDA QMSR.
Verification and validation are different questions
Verification asks: did we build the design right? It shows that design outputs meet design inputs (ISO 13485 clause 7.3.6).
Validation asks: did we build the right design? It shows that the product meets the requirements for its specified application or intended use (clause 7.3.7).
The trace matrix keeps the two apart. Design inputs close by verification; user needs close by validation.
Plan verification before testing
Clause 7.3.6 asks for documented verification plans that include methods, acceptance criteria and, where appropriate, statistical techniques with the reasoning for sample size. A good protocol also records:
the design inputs it covers
the test articles, with part number, revision and build
the test configuration and conditions
the equipment, with calibration status
the risk controls it verifies, since ISO 14971 asks that each risk control is verified as implemented and as effective
Where the device must connect or interface with other devices for its intended use, verification must confirm that the outputs meet the inputs when so connected. Approve the protocol before testing starts.
Justify the sample size
The standard does not set sample sizes. It asks for the reasoning. One common approach for a pass or fail test with zero failures allowed is the success-run calculation: n = ln(1 - C) / ln(R), where C is the confidence and R the reliability to be shown. For 95 % confidence of at least 90 % reliability, n = ln(0.05) / ln(0.90) = 28.4, so 29 samples with no failures.
Other reasons are just as valid when they are written down: a sample size set by a product standard, a variables test whose statistics are worked out from the data, or a risk-based rule in your statistical techniques procedure. What is not valid is a number with no reason.
Treat failures as information
Record the raw data, the article identity and any deviation from the protocol. When a test fails, investigate before retesting. If the design must change, the change goes through design change control (clause 7.3.9), with its significance and its effect on other requirements assessed, and the affected tests are repeated.
Validate on representative product
Clause 7.3.7 asks for documented validation plans with methods, acceptance criteria and, where appropriate, sample-size reasoning. It then adds three points that often catch teams out:
Validation uses representative product: initial production units, batches or their equivalents. The reason for the choice is recorded.
Validation includes clinical or performance evaluation as regulations require. A device used for that evaluation is not treated as released to the customer.
Validation is finished before the product is released to the customer.
Where the intended use needs the device to connect or interface with other devices, validation includes them. Usability validation under IEC 62366-1 is often part of design validation.
Product built by hand in the lab is rarely representative. If pilot lots from the production line are not yet available, record why the product used is equivalent.
Transfer the design to manufacturing
Clause 7.3.8 asks for documented transfer procedures that make sure design outputs are verified as suitable for manufacturing before they become final production specifications, and that production capability can meet product requirements. The results and conclusions are recorded.
A transfer checklist usually confirms that:
drawings, specifications and the bill of materials are released
the essential characteristics are on drawings and inspection plans
production processes are validated and process risks assessed
inspection methods and gauges are in place and calibrated
suppliers and outsourced processes are approved
labeling and instructions for use are approved
people are trained
Capability is shown with data, for example pilot lots measured on the essential characteristics against a capability rule in your statistical techniques procedure.
Close the loop before release
Before release, the final design review should see every trace matrix row closed, the risk management report approved (ISO 14971 asks for a review that the plan was carried out and the overall residual risk is acceptable), validation and transfer complete, and the marketing authorization for each market in place or planned. The records then go into the design and development file required by clause 7.3.10.
Putting it into practice
The Design Control Kit includes the Design Verification Protocol and Report, the Design Validation Protocol and Report, the Design Transfer Checklist and the Design Change Impact Assessment, used under two step-by-step procedures. The Excel trace matrix shows which inputs are not yet verified and which user needs are not yet validated.
Frequently asked questions
Can verification and validation use the same test?
Sometimes a single study provides evidence for both, but the two questions and their acceptance criteria stay separate, and the trace matrix records each.
Does every verification test need a statistical sample size?
Clause 7.3.6 says statistical techniques are used where appropriate. An inspection of a single drawing dimension may need one sample; a strength test usually needs a justified sample size.
When is validation not complete?
Until the product meets its user needs on representative product and the results are recorded. Clause 7.3.7 asks that this happens before release to the customer.
Building a complete quality system? Build Your QMS lets you choose ISO 13485 + FDA QMSR, Dual-Standard or ISO 9001:2026 procedures in one place, and applies volume discounts automatically: 20% off 5–9 procedures, 35% off 10–19, 50% off 20–39 and 60% off 40 or more.
Not sure where your quality system stands? Take the free QMS gap check: about 20 questions, an instant report of your gaps by clause, and the procedures that close each one.
Just getting started? The free Startup Quality Plan shows which procedures you need now, which can wait, and how long they take to put in place.



Comments