Using PRP Verification Results: Trends, the Quarterly Analysis and the Annual PRP Review
Reviewed by Aaron Lyon, President of A.P. Lyon and former Director of Quality Assurance and International Regulatory, with more than 30 years in medical device quality. Last reviewed November 27, 2026.
A year of PRP inspections produces hundreds of scores and findings. Filed away, they prove only that inspections happened. Analysed, they show which areas are slipping, which PRPs are weakest and whether last quarter's corrective actions worked. ISO 22000 expects that analysis. This guide shows how to do it on a monthly, quarterly and annual cycle.
Every summary of a standard here is in our own words. For how the inspections themselves are scored, see PRP Verification Inspections: How to Score Them and Track Findings.
What ISO 22000 asks for
ISO 22000:2018 clause 8.8 asks the food safety team to analyse the results of verification as an input to the evaluation of the food safety management system. Clause 9.1 goes further. Data from monitoring, from verification of PRPs and the hazard control plan, and from internal and external audits are analysed to:
confirm that the system performs as planned
identify a need to update or improve it
identify trends that show more potentially unsafe product or process failures
plan the internal audit programme
show that corrections and corrective actions are effective
The results are kept and reported to top management for management review and the system update. PRP inspection results are one of the main data sources for every point on that list.
Monthly: look for areas slipping
Each month, Quality Assurance should look at:
Inspections due or overdue by area. An area that has not been inspected on time is a gap in verification, whatever its last score.
Areas below target this month.
Open and overdue findings, by area and owner.
Findings flagged for corrective action: critical, repeat or overdue.
This is a short review with the area owners, aimed at getting overdue inspections done and overdue findings closed.
Quarterly: the analysis of verification results
Each quarter, set the period to the quarter and work out:
The overall PRP inspection score: items OK divided by items checked across every inspection in the quarter. Compare it with the target and with the previous quarter.
Scores by area: which areas are below target, and which are getting worse.
Scores by PRP element: rank the elements from weakest to strongest. An element that is weak across many areas points to a problem with the PRP itself, not one area.
Findings: how many were raised, how many were critical, how many were repeats, and how many are still open.
Record the results with the other verification data (CCP and OPRP deviations, environmental monitoring, product testing, complaints, audits) in the quarterly analysis report, and decide the actions. In our food safety system this is FORM 9002-1-F under the Analysis of Verification Results Procedure, where the PRP inspection score is one of the listed measures.
Reading the trends
A few patterns come up again and again:
A slow fall in one area's score usually means something changed: a new shift pattern, a new supervisor, more production, or equipment getting older.
One element weak everywhere, such as utilities or hygiene facilities, usually means the PRP or its procedure needs to change, not the people.
Repeat findings on the same item mean the corrective action did not reach the cause.
Scores always at 100% are worth a second look. Either the site is excellent or the inspection has become a box-ticking exercise. Rotate inspectors and shifts and see whether the score holds.
Annually: the PRP review
At least once a year, and after any significant change, food safety incident or repeated failure, the food safety team should review the PRPs and confirm they are still suitable, implemented and effective. ISO 22000:2018 expects the food safety team to approve the PRPs. A yearly review of the evidence is how a team keeps that approval meaningful.
Set the period to the year and bring:
the element ranking for the year, weakest first
the areas with the lowest scores and the most findings
the repeat findings and the corrective actions raised from them
any item excluded as not applicable, to confirm the reason still holds
Then decide what changes: a PRP procedure, an inspection frequency, a check item, a training need, or a capital repair. Where verification shows a PRP is not effective, also consider whether the hazard analysis, the OPRPs or the CCPs need to change. Record the review and the actions decided.
Common mistakes
Reporting the overall score only, which hides the area or element that is failing.
Changing how the score is counted partway through the year, so the trend means nothing.
No link from the analysis to actions, owners and dates.
An annual PRP review that only re-signs the register without looking at the year's results.
Putting it into practice
The PRP Verification Workbook has a dashboard that works out every figure above for any period you choose: the overall score against target, a table by area with overdue inspections and open findings, a table of the 20 PRP elements ranked weakest first, and a 12-month trend chart. Copy the quarterly score straight into your analysis report.
Frequently asked questions
How often should PRP results be analysed?
ISO 22000 does not set a frequency. A monthly operational review and a quarterly analysis that feeds management review is a common and workable pattern. Our food safety system analyses verification results at least quarterly.
Should PRP scores go to management review?
Yes. ISO 22000 clause 9.1 sends the results of the analysis to top management as an input to management review and to the system update.
What if an element is weak but every finding was closed?
Closing findings fixes the problem in front of you. If the same element keeps failing, the PRP, its procedure or its resources need to change. That is a decision for the annual PRP review, or sooner if the trend is getting worse.
Building a complete food safety system? The Food Safety Management System Complete includes a food safety manual, a food safety plan and HACCP workbook, 57 procedures and 104 forms, written to ISO 22000:2018, FSSC 22000 Version 7 and FDA 21 CFR 117.
Not sure where your quality system stands? Take the free QMS gap check: about 20 questions, an instant report of your gaps by clause, and the procedures that close each one.
Just getting started? The free Startup Quality Plan shows which procedures you need now, which can wait, and how long they take to put in place.



Comments